我有如下的项目时间表。我需要从第一开始的会议开始wbs。在开场之前,我使用了定制的wbs代码( M1,M2,M3,M4 ).起作用了。从开始在病房的会议开始,我需要开始11.1 1.2,2,2.1,2.2等等。
现有计划
WBS Task name
1 M1: Milestone1
2 M2: Milestone2
3 M3: Milestone3
4 M4: Milestone4
5 Kick-off meeting
6 Requirement
6.1. Requirement collection
6.2. Requirement priority
6.3. Finalise requirements
7 Design
7.1 High level design
7.2 Low level design
8 Implementation
8.1 coding
8.2 code review
9 Testing
9.1 Test plan
9.2 Test case preparation
9.3 Start Testing
10 Delivery
10.1 Deliver to customer
10.2 Release resource我需要改变WBS以上的wbs代码如下所示。
预期进度
WBS Task name
M1: Milestone1
M2: Milestone2
M3: Milestone3
M4: Milestone4
1 Kick-off meeting
2 Requirement
2.1. Requirement collection
2.2. Requirement priority
2.3. Finalise requirements
3 Design
3.1 High level design
3.2 Low level design
4 Implementation
4.1 coding
4.2 code review
5 Testing
5.1 Test plan
5.2 Test case preparation
5.3 Start Testing
6 Delivery
6.1 Deliver to customer
6.2 Release resource我试过使用Project -> wbS ->定义代码和重编号,但两者都无法工作。
发布于 2017-12-31 14:34:54
使用自定义大纲代码,而不是内置WBS字段。那你想怎么做都行。命名自定义代码CWBS或PWBS或类似的东西,这样您就可以区分它们。